Hyderabad Sukkur Motorway Update

As of April, 2021 The federal government deferred approval of Rs192 billion worth of Hyderabad-Sukkur motorway project due to proposed changes in its financing model, which now seeks Rs76 billion from the budget compared to the original plan of constructing the road with private sector funding.

The Central Development Working Party (CDWP), which has a mandate to approve public sector projects, referred back the scheme to the Public Private Partnership (PPP) Authority for vetting the budget demand of Rs 76 billion.

 

JANUARY 2024 UPDATE

The National Highway Authority (NHA) has ended its partnership with M/s Techno-CMC (TECMC) Private Limited for the Sukkur-Hyderabad Motorway (M-6) project, the largest Public-Private Partnership (PPP) endeavor in Pakistan, valued at Rs307 billion. This decision comes after the Concessionaire failed to secure financial closure within the stipulated timeframe.

The termination of this agreement is expected to cause further delays in the completion of this significant infrastructure project, according to official sources.

 

 

M6 - Hyderabad Sukkur Motorway

Interchange Junction Location
Jamshoro 1 M-9 Jamshoro
N-55 2 Jamshoro Sehwan Rd
Hyderabad 3 N-5
Matiari 4 Tando Allah Yar Rd
Oderolal 5 Khyber Rd
Tando Adam 6 Bhit Shah Rd
Shahdadpur 7 Hala Rd
Nawabshah 8 Sakrand Rd
Daur 9 Daur-Moro Rd
Padidan 10 Padidan-N.Feroze Rd
Bhiria Road 11 Bhiria Road
Mehrabpur 12 Mehrabpur Rd
Gadeji 13 N-5
Khairpur-Larkana 14 Khairpur-Larkana Rd
Khairpur 15 Khairpur Rd